Boutique Hotel
Sixty guest rooms, lobby, all-day restaurant and spa fit-out
The challenge
Sixty rooms meant sixty of everything a repeat unit where a small detailing error multiplies. Guest-to-guest acoustics and bathroom waterproofing were the two risks that could not be fixed after handover.
Our solution
We built and signed off a full mock-up room before mass production: partition build-up, door seal, bathroom tanking, joinery and lighting were all tested in that one room, then replicated.
Execution sequence
Mock-up room in month three, mass fit-out across months four to ten, public areas and spa in parallel, then commissioning and soft launch.
Result
Bathroom water testing passed across all rooms with no leaks recorded during the defect-liability period. Room-to-room acoustics met the brand standard.
“The mock-up room saved us from making the same mistake sixty times.”